Magnitude of Construction Cost and Schedule Overruns in Public Work Projects. (18th December 2013)
- Record Type:
- Journal Article
- Title:
- Magnitude of Construction Cost and Schedule Overruns in Public Work Projects. (18th December 2013)
- Main Title:
- Magnitude of Construction Cost and Schedule Overruns in Public Work Projects
- Authors:
- Shrestha, Pramen P.
Burns, Leslie A.
Shields, David R. - Other Names:
- Jha Manoj Academic Editor.
- Abstract:
- Abstract : This study analyzed 363 Clark County Department of Public Works (CCDPW) projects to determine construction cost and schedule overruns in various types and sizes of the projects. The sample projects were constructed from 1991 to 2008, with a total construction cost of $1.85 billion, equivalent to 2012 cost. A one-factor ANOVA test was conducted to determine whether construction cost and schedule overruns significantly varied based on types and sizes of the projects. The study showed that large, long-duration projects had significantly higher cost and schedule overruns than smaller, short-duration projects.
- Is Part Of:
- Journal of construction engineering. Volume 2013(2013)
- Journal:
- Journal of construction engineering
- Issue:
- Volume 2013(2013)
- Issue Display:
- Volume 2013, Issue 2013 (2013)
- Year:
- 2013
- Volume:
- 2013
- Issue:
- 2013
- Issue Sort Value:
- 2013-2013-2013-0000
- Page Start:
- Page End:
- Publication Date:
- 2013-12-18
- Subjects:
- Construction projects -- Periodicals
Civil engineering -- Periodicals
Engineering -- Periodicals
Construction industry -- Periodicals
Civil engineering
Construction industry
Construction projects
Engineering
Electronic journals
Periodicals
624 - Journal URLs:
- https://www.hindawi.com/journals/jcen/ ↗
- DOI:
- 10.1155/2013/935978 ↗
- Languages:
- English
- ISSNs:
- 2356-7295
- Deposit Type:
- Legaldeposit
- View Content:
- Available online (eLD content is only available in our Reading Rooms) ↗
- Physical Locations:
- British Library HMNTS - ELD Digital store
- Ingest File:
- 10831.xml