Evaluation of site managers' hindrances towards optimal utilisation of construction resources. Issue 3 (1st July 2014)
- Record Type:
- Journal Article
- Title:
- Evaluation of site managers' hindrances towards optimal utilisation of construction resources. Issue 3 (1st July 2014)
- Main Title:
- Evaluation of site managers' hindrances towards optimal utilisation of construction resources
- Authors:
- Ayodeji Fapohunda, Julius
- Abstract:
- Abstract : Purpose: – The purpose of this paper is to delineate different types of site manager attributes that significantly contribute to construction project management efficiency and evaluate the factors that hinder the site manager during construction production processes. Towards efficient resources utilisation, site managers require various qualities and potentials. Design/methodology/approach: – To achieve valid result, the research study was triangulated by exploring literature, which was augmented with both quantitative questionnaire and qualitative interview research methods. The research data were collected in the UK building industry. Findings: – It was found that the barriers that often affect efficient utilisation of construction resources in the industry are poor communication, disagreement, misunderstandings, bad weather, union strikes and construction participants' personality conflicts. This research study presents severity of site manager's hindrances, factors that affect site manager's efficiencies, solutions to minimise the hindrances on site manager's efficient performance and factors that should be constant towards site mangers' efficient performance. Among these solutions found evident that will enhance site managers' performance and minimise the effect of the hindrances are an enhanced planning and adequate programming of construction resources before and during project execution, rational team building and an efficient construction team forAbstract : Purpose: – The purpose of this paper is to delineate different types of site manager attributes that significantly contribute to construction project management efficiency and evaluate the factors that hinder the site manager during construction production processes. Towards efficient resources utilisation, site managers require various qualities and potentials. Design/methodology/approach: – To achieve valid result, the research study was triangulated by exploring literature, which was augmented with both quantitative questionnaire and qualitative interview research methods. The research data were collected in the UK building industry. Findings: – It was found that the barriers that often affect efficient utilisation of construction resources in the industry are poor communication, disagreement, misunderstandings, bad weather, union strikes and construction participants' personality conflicts. This research study presents severity of site manager's hindrances, factors that affect site manager's efficiencies, solutions to minimise the hindrances on site manager's efficient performance and factors that should be constant towards site mangers' efficient performance. Among these solutions found evident that will enhance site managers' performance and minimise the effect of the hindrances are an enhanced planning and adequate programming of construction resources before and during project execution, rational team building and an efficient construction team for project, in addition to adequate information dissemination and transfer of knowledge. Originality/value: – The adequate implementation of the solutions presented in this paper will not only enhance the performance of site managers on resources utilisation but will also augment client satisfactions. … (more)
- Is Part Of:
- Journal of engineering, design and technology. Volume 12:Issue 3(2014)
- Journal:
- Journal of engineering, design and technology
- Issue:
- Volume 12:Issue 3(2014)
- Issue Display:
- Volume 12, Issue 3 (2014)
- Year:
- 2014
- Volume:
- 12
- Issue:
- 3
- Issue Sort Value:
- 2014-0012-0003-0000
- Page Start:
- 348
- Page End:
- 363
- Publication Date:
- 2014-07-01
- Subjects:
- Construction management -- Construction production processes -- Project management -- Resources utilisation -- Site managers' attributes -- Site managers' performance
Engineering -- Periodicals
Engineering design -- Periodicals
Industrial design -- Periodicals
Technology -- Periodicals
620.005 - Journal URLs:
- http://firstsearch.oclc.org ↗
http://info.emeraldinsight.com/products/journals/journals.htm?PHPSESSID=vf0n9oto7i08tel2huutrd3n81&id=jedt ↗
http://rzblx1.uni-regensburg.de/ezeit/warpto.phtml?colors=7&jour%5Fid=84581 ↗
http://www.emeraldinsight.com/ ↗ - DOI:
- 10.1108/JEDT-03-2012-0013 ↗
- Languages:
- English
- ISSNs:
- 1726-0531
- Deposit Type:
- Legaldeposit
- View Content:
- Available online (eLD content is only available in our Reading Rooms) ↗
- Physical Locations:
- British Library DSC - 4978.840000
British Library DSC - BLDSS-3PM
British Library HMNTS - ELD Digital store - Ingest File:
- 9891.xml