Analyzing the relationship between project productivity and environment factors in the use case points method. Issue 9 (11th May 2017)
- Record Type:
- Journal Article
- Title:
- Analyzing the relationship between project productivity and environment factors in the use case points method. Issue 9 (11th May 2017)
- Main Title:
- Analyzing the relationship between project productivity and environment factors in the use case points method
- Authors:
- Azzeh, Mohammad
Nassif, Ali Bou - Abstract:
- Abstract: Project productivity is a key factor for producing effort estimates from use case points (UCP), especially when the historical dataset is absent. The first versions of UCP effort estimation models used a fixed number or very limited numbers of productivity ratios for all new projects. These approaches have not been well examined over a large number of projects, so the validity of these studies was a matter for criticism. The newly available large software datasets allow us to perform further research on the usefulness of productivity for effort estimation of software development. Specifically, we studied the relationship between project productivity and UCP environmental factors, as they have a significant impact on the amount of productivity needed for a software project. Therefore, we designed 4 studies, using various classification and regression methods, to examine the usefulness of that relationship and its impact on UCP effort estimation. The results we obtained are encouraging and show potential improvement in effort estimation. Furthermore, the efficiency of that relationship is better over a dataset that comes from industry because of the quality of data collection. Our comment on the findings is that it is better to exclude environmental factors from calculating UCP and make them available only for computing productivity. The study also encourages project managers to understand how to better assess the environmental factors, as they do have a significantAbstract: Project productivity is a key factor for producing effort estimates from use case points (UCP), especially when the historical dataset is absent. The first versions of UCP effort estimation models used a fixed number or very limited numbers of productivity ratios for all new projects. These approaches have not been well examined over a large number of projects, so the validity of these studies was a matter for criticism. The newly available large software datasets allow us to perform further research on the usefulness of productivity for effort estimation of software development. Specifically, we studied the relationship between project productivity and UCP environmental factors, as they have a significant impact on the amount of productivity needed for a software project. Therefore, we designed 4 studies, using various classification and regression methods, to examine the usefulness of that relationship and its impact on UCP effort estimation. The results we obtained are encouraging and show potential improvement in effort estimation. Furthermore, the efficiency of that relationship is better over a dataset that comes from industry because of the quality of data collection. Our comment on the findings is that it is better to exclude environmental factors from calculating UCP and make them available only for computing productivity. The study also encourages project managers to understand how to better assess the environmental factors, as they do have a significant impact on productivity. … (more)
- Is Part Of:
- Journal of software. Volume 29:Issue 9(2017)
- Journal:
- Journal of software
- Issue:
- Volume 29:Issue 9(2017)
- Issue Display:
- Volume 29, Issue 9 (2017)
- Year:
- 2017
- Volume:
- 29
- Issue:
- 9
- Issue Sort Value:
- 2017-0029-0009-0000
- Page Start:
- n/a
- Page End:
- n/a
- Publication Date:
- 2017-05-11
- Subjects:
- environmental factors -- software effort estimation -- software productivity -- use case points
Software engineering -- Periodicals
Computer software -- Development -- Periodicals
Software maintenance -- Periodicals
005.1 - Journal URLs:
- http://onlinelibrary.wiley.com/journal/10.1002/(ISSN)2047-7481 ↗
http://onlinelibrary.wiley.com/ ↗ - DOI:
- 10.1002/smr.1882 ↗
- Languages:
- English
- ISSNs:
- 2047-7473
- Deposit Type:
- Legaldeposit
- View Content:
- Available online (eLD content is only available in our Reading Rooms) ↗
- Physical Locations:
- British Library DSC - BLDSS-3PM
British Library HMNTS - ELD Digital store - Ingest File:
- 4570.xml