Evaluating contract claims. (2020)
- Record Type:
- Book
- Title:
- Evaluating contract claims. (2020)
- Main Title:
- Evaluating contract claims
- Further Information:
- Note: John Mullen and R. Peter Davison.
- Authors:
- Davison, R. Peter
Mullen, John, 1959- - Contents:
- Reviews xvii Preface xxi Acknowledgements xxvii 1 Introduction 1 1.1 The Legal Basis 2 1.1.1 Forms of Contract 2 1.2 The Standard of Substantiation 4 1.2.1 SCL Delay and Disruption Protocol 5 1.2.2 Direct and Time Consequences 7 1.2.3 Duty to Mitigate 9 1.3 Risks 12 1.3.1 Design Risks 12 1.3.2 Design Review 14 1.3.3 Professional Indemnity Insurance 14 1.3.4 Risk Analysis and Management 14 1.3.5 Risk Registers 16 1.3.6 Risks and Records 17 1.3.7 Reimbursable Risks 20 1.3.8 Non-reimbursable Risks 21 1.4 Sources of Change 22 1.4.1 The Process of Analysis 22 1.4.2 Inadequate Pre-contract Design and Documentation 23 1.4.3 Design Development and Approval 26 1.4.4 Access or Possession 27 1.4.5 Early Taking over or Beneficial Use 28 1.4.6 Changes in Employer Requirements 28 1.4.7 Contract Documents 29 1.4.8 Unforeseeable Occurrences 30 1.4.9 Breach of Contract 31 1.5 Summary 32 2 Establishing the Base 33 2.1 Planned Change 34 2.1.1 Ordered Variations 36 2.1.1.1 Fair Rates and Prices 39 2.1.2 Changes in Quantities 41 2.1.2.1 Quantities and Conditions 43 2.1.3 Preferential Engineering 44 2.1.4 Value Engineering 45 2.1.5 Unconfirmed Instructions 46 2.2 Unplanned Change 47 2.3 Programmes and Method Statements 47 2.3.1 The Status of Programmes 47 2.3.2 Programmes and Resources 52 2.3.2.1 Method Statements 52 2.3.3 The SCL Delay and Disruption Protocol 54 2.3.4 A Partial Programme 55 2.3.5 Limitations on Liability 55 2.4 Summary 56 3 Effect of Change on Programmes of Work 57 3.1 Use ofReviews xvii Preface xxi Acknowledgements xxvii 1 Introduction 1 1.1 The Legal Basis 2 1.1.1 Forms of Contract 2 1.2 The Standard of Substantiation 4 1.2.1 SCL Delay and Disruption Protocol 5 1.2.2 Direct and Time Consequences 7 1.2.3 Duty to Mitigate 9 1.3 Risks 12 1.3.1 Design Risks 12 1.3.2 Design Review 14 1.3.3 Professional Indemnity Insurance 14 1.3.4 Risk Analysis and Management 14 1.3.5 Risk Registers 16 1.3.6 Risks and Records 17 1.3.7 Reimbursable Risks 20 1.3.8 Non-reimbursable Risks 21 1.4 Sources of Change 22 1.4.1 The Process of Analysis 22 1.4.2 Inadequate Pre-contract Design and Documentation 23 1.4.3 Design Development and Approval 26 1.4.4 Access or Possession 27 1.4.5 Early Taking over or Beneficial Use 28 1.4.6 Changes in Employer Requirements 28 1.4.7 Contract Documents 29 1.4.8 Unforeseeable Occurrences 30 1.4.9 Breach of Contract 31 1.5 Summary 32 2 Establishing the Base 33 2.1 Planned Change 34 2.1.1 Ordered Variations 36 2.1.1.1 Fair Rates and Prices 39 2.1.2 Changes in Quantities 41 2.1.2.1 Quantities and Conditions 43 2.1.3 Preferential Engineering 44 2.1.4 Value Engineering 45 2.1.5 Unconfirmed Instructions 46 2.2 Unplanned Change 47 2.3 Programmes and Method Statements 47 2.3.1 The Status of Programmes 47 2.3.2 Programmes and Resources 52 2.3.2.1 Method Statements 52 2.3.3 The SCL Delay and Disruption Protocol 54 2.3.4 A Partial Programme 55 2.3.5 Limitations on Liability 55 2.4 Summary 56 3 Effect of Change on Programmes of Work 57 3.1 Use of Programmes 58 3.1.1 Provisional Sums in Programmes 60 3.1.2 The Base Cost 63 3.2 Use of As-Built Programmes 64 3.2.1 Sources of Information for As-Built Programmes 65 3.2.2 Constant Resource/Continuous Working 66 3.2.3 Recording of Completion 67 3.3 Change Without Overall Prolongation 67 3.3.1 Who Owns the Float? 68 3.4 Prolongation of the Works 74 3.5 Analysis of Time and Delay 77 3.5.1 Introduction 77 3.5.2 Basic Requirements 82 3.5.3 Float and Acceleration 86 3.5.4 Concurrent Delays 88 3.5.5 ‘Dot on’ 98 3.5.6 Concurrency and the Contractor’s Financial Claims 100 3.5.7 Delay Analysis Techniques 103 3.5.7.1 Impacted as Planned 104 3.5.7.2 Time Impact Analysis 108 3.5.7.3 Collapsed As-Built Analysis 111 3.5.7.4 As-Planned Versus As-Built Programmes 113 3.5.7.5 Windows Analysis 115 3.5.7.6 Software 116 3.5.7.7 Building Information Modelling 118 3.5.7.8 Case Law 120 3.5.7.9 Conclusions 123 3.5.8 Assessment of Productivity 125 3.5.8.1 Tender Productivity 126 3.5.8.2 Achievable Productivity 127 3.5.8.3 Actual Productivity After a Change 127 3.5.9 Sources of Productivity Data 128 3.5.9.1 The Fundamental Principles 128 3.5.9.2 Relevant Quantities 128 3.5.9.3 Equipment and Methods 129 3.5.9.4 Sustainable Outputs 130 3.5.9.5 Recalculation Using Efficiency Factors 130 3.5.10 Effect on Contractor’s Plant and Equipment 131 3.5.10.1 Working Plant and Equipment 132 3.5.10.2 Site Facilities and Equipment 133 3.5.11 Duty to Mitigate 134 3.6 Summary 135 4 Sources of Financial Information for Evaluation 137 4.1 The Contract Provisions 139 4.1.1 Cost 139 4.1.2 Loss and Expense 141 4.1.3 To Ascertain 142 4.2 Tender Documents and Information 145 4.2.1 Entire Agreements 146 4.2.2 Misstatements and Misrepresentation 147 4.2.3 Mistakes in Tenders 148 4.2.4 The Conditions for, and Character of, the Works 149 4.3 Tender Calculations and Assumptions 149 4.4 Cost Records 151 4.4.1 Identification of Invoices 151 4.4.2 Discounts and Credit Notes 152 4.4.3 Bulk Discounts 153 4.4.4 Coding Systems 154 4.4.5 Timing of Costs 154 4.4.6 Cost Transfers and Accruals 155 4.4.7 Final Accounts and Economic Duress 156 4.5 Accounting Information 158 4.5.1 Financial Accounts 158 4.5.2 Management Accounts 159 4.5.3 Exceptional Items 161 4.6 External Information 161 4.7 Summary 162 5 Evaluation of the Direct Consequences of Change 165 5.1 Unit Rates and Prices or Actual Costs? 166 5.2 Unit Rates and Prices 167 5.2.1 The FIDIC Forms of Contract 172 5.2.2 Measurement of Work 173 5.2.3 Design and Build/Schedule of Rates 175 5.2.4 Status of Contract Rates and Prices 176 5.2.5 Errors in Rates and Prices 177 5.3 The Valuation ‘Fences’ 184 5.3.1 The ‘Fences’ 185 5.3.2 ‘Conditions’ and ‘Character’ 185 5.3.2.1 Change in Conditions 187 5.3.2.2 Change in Character 188 5.3.3 New Rates 189 5.3.4 Valuation of Variations in Quantity 190 5.3.5 Effect of Variations on Other Work 196 5.4 Inclusion of Preliminaries and General Items 197 5.5 Percentage Adjustments 200 5.5.1 Percentages in Variation Valuation 200 5.5.2 Threshold Percentages 201 5.5.2.1 Criteria for Judging Change in the Amount of Work 202 5.5.2.2 Which Rates are to Be Amended? 203 5.5.2.3 What Rules Apply? 203 5.5.3 Percentages for Defective or Incomplete Work, etc. 204 5.5.4 Percentage Caps on Adjustments 205 5.6 Valuation Using Day work Provisions 205 5.7 Use of Actual Costs 210 5.7.1 The NEC Suite of Contracts – Introduction 211 5.7.2 The NEC Suite of Contracts – Forecast or Actual Cost? 213 5.7.3 The NEC Suite of Contracts – Defined Cost 218 5.7.4 The NEC Suite of Contracts – Disallowed Cost 221 5.7.5 The NEC Suite of Contracts –The Fee and Other Agreed Rates 223 5.7.6 The NEC Suite of Contracts – Objectives 224 5.8 Unit Costs 225 5.8.1 Labour Costs 229 5.8.1.1 Gang Rates 229 5.8.1.2 Supervision 230 5.8.2 Use of Norms in Evaluation 231 5.8.3 Plant and Equipment Costs 234 5.8.3.1 Plant and Equipment Cost Rates 235 5.8.3.2 External Hire Charges 240 5.8.4 Materials Costs 241 5.8.5 Overheads and Profit 243 5.9 Subcontractor and Supplier Costs 245 5.9.1 Subcontractors 246 5.9.1.1 Nominated or Named Subcontractors 246 5.9.1.2 Domestic Subcontractors 249 5.9.2 Package Equipment Suppliers 250 5.9.2.1 Example of Change Calculation for Package Equipment 252 5.10 Valuation of Omissions 253 5.11 Add and Omit Variations 254 5.12 Quantum Meruit 257 5.12.1 No Contract or Agreement as to Price 258 5.12.2 Contract Only Says Reasonable Sum 259 5.12.3 Work Outside of Contract 259 5.12.4 Cardinal Change 260 5.12.5 How to Calculate 263 5.13 Valuation in Advance 265 5.14 Requirements for Notices 269 5.14.1 Notice in Relation to Unit Rates 270 5.14.2 Notice in Relation to a Quotation or Proposal 273 5.14.3 Notice as a Condition Precedent and Other Sanctions 275 5.14.4 Further Considerations 277 5.15 Summary 278 6 Evaluation of the Time Consequences of Change 279</ … (more)
- Edition:
- Third edition
- Publisher Details:
- Hoboken, NJ, USA : John Wiley & Sons, Inc
- Publication Date:
- 2020
- Copyright Date:
- 2020
- Extent:
- 1 online resource
- Subjects:
- 692/.8
Buildings -- Maintenance -- Costs
Construction contracts
Construction industry -- Law and legislation
Remedies (Law)
Claims
Buildings -- Maintenance -- Costs
Claims
Construction contracts
Construction industry -- Law and legislation
Remedies (Law)
Electronic books - Languages:
- English
- ISBNs:
- 9781118918135
1118918134
9781118917800
1118917804
9781118918128
1118918126 - Related ISBNs:
- 9781118918142
1118918142 - Notes:
- Note: Includes bibliographical references and index.
Note: Description based on online resource; title from digital title page (viewed on December 06, 2019). - Access Rights:
- Legal Deposit; Only available on premises controlled by the deposit library and to one user at any one time; The Legal Deposit Libraries (Non-Print Works) Regulations (UK).
- Access Usage:
- Restricted: Printing from this resource is governed by The Legal Deposit Libraries (Non-Print Works) Regulations (UK) and UK copyright law currently in force.
- View Content:
- Available online (eLD content is only available in our Reading Rooms) ↗
- Physical Locations:
- British Library HMNTS - ELD.DS.456443
- Ingest File:
- 02_594.xml